Most machining quotes arrive as a single number per part. When they are itemised, the lines are usually material, machining, setup, finish and a margin — and each one can be sanity checked with arithmetic you can do yourself.
Swipe the table sideways for the remaining columns →
| Line | How it is calculated | Per part |
|---|---|---|
| Material | 0.71 kg stock at $20.94/kg, 25% allowance | $27.14 |
| Cycle time | 18.5 min at $110/hr | $33.97 |
| Setup | 146 min ÷ 10 at $110/hr | $26.77 |
| Shop cost | material + cycle + setup | $87.88 |
| Margin | 30% on lot cost | $26.36 |
| Price | per part | $114.24 |
Numbers come from the same model that runs on the calculator page, at default inputs.
Multiply stock mass by the metal price. If the mass looks too low for the envelope, the shop is assuming near-net stock — fine for a plate, wrong for a bar. If the price per kilogram looks like a mill's tonnage rate rather than a distributor's cut-to-size rate, the quote is optimistic and something else is carrying the cost.
Setup divided by quantity should be visible and should fall as quantity rises. A quote where setup stays constant per part across quantities is not really quoting quantities. A quote with no setup line at all is either amortising it into the rate or hiding a one-off charge elsewhere.
Inspection, certification, first-article reports, material certificates, packing and freight are all legitimately extra and all routinely omitted from a first quote. Ask which of them apply before comparing two quotes as if they were equivalent — most "cheaper" quotes are cheaper because something was left out.