Lead time is quoted as a single number and behaves like two different things depending on quantity. At low volume it is queue time: your job waits behind other jobs, and the machining is a rounding error. At high volume it becomes machine time, and that is when the date starts moving. Knowing which regime you are in tells you what to argue about — the schedule, or the quantity.
Swipe the table sideways for the remaining columns →
| Quantity | Cycle time per part | Machine hours for the lot | Lead time |
|---|---|---|---|
| 1 | 23.3 min | 0.4 hr | 6 days |
| 10 | 18.5 min | 3.1 hr | 6 days |
| 100 | 14.7 min | 24.5 hr | 9 days |
| 1000 | 11.7 min | 194.8 hr | 30 days |
Cycle time per part falls with quantity while machine hours for the lot rise. Lead time barely moves until the lot is large enough for spindle time to overtake queue time.
Below a few dozen pieces, lead time is dominated by things that have nothing to do with your part: how full the shop's schedule is, whether the material is in stock, whether the programmer is on holiday. Machining a ten-piece lot takes a few hours on the machine and about a week on the calendar. Above a few hundred pieces the arithmetic flips — the machine hours become days, then weeks, and the shop is no longer guessing.
Most common alloys are stocked and arrive in days. The exceptions are the ones that cost money to hold: titanium, some stainless grades, unusual thicknesses, anything requiring a mill certificate for a specific heat. A shop that quotes two weeks and then takes five is usually waiting on metal, not on a machine. If the date matters, the question to ask is not "how busy are you" but "is the material on the floor".
A rush charge buys your job a different position in the queue, not a faster spindle. That is why it is priced as a percentage rather than an hourly rate, and why it is hard to negotiate on small jobs — there is no slack to compress. The cheapest way to shorten a lead time is usually to remove a step: a standard alloy instead of an exotic one, a finish that can be batched, or a tolerance that does not require a separate inspection visit.